The Facility
Bechtel Power Corporation built a power plant in Northampton, Pennsylvania for U.S. Generating Company. The power plant burns culm, a lower quality coal rejected from use in previous decades. By using culm as the fuel, U.S. Generating will clean up a solid disposal site. The power plant contains the usual systems including cooling towers and demineralizers that produce waste brines in the course of their operation.
Project Overview
Environmental regulations require that no liquids be discharged to the environment. In this case the LeHigh River. A system was required that would recover at least 95% of the water from the waste brine steam for spraying onto an ash pile.
Scope of Service
Aquatech worked closely with Bechtel to develop an evaporator system to meet zero liquid discharge requirements. Since there is an excess of low cost steam in the plant, a two effect evaporator was selected rather than an electric driven vapor compression system. The maximum waste brine flow is 100 gpm and can be many combinations of cooling tower blowdown and demineralizer regenerant waste. The waste brine is high in calcium sulfate and silica. To prevent scaling on the evaporator heat transfer surface the first effect (the more concentrated effect) is designed to operate “seeded.” Calcium sulfate crystals are circulated through the system. Instead of scale forming on the heat transfer surface, the scale forms on the circulating crystals. The 98gpm of distillate recovered will have less than 10 ppm dissolved salts. The purified water will be combined with boiler condensate and used as make-up water for the demineralizer system. The 2 gpm concentrated brine is combined with pretreatment sludge blowdown and pumped to an ash conditioning tank. Installation of the evaporator commenced in October 1993 and commissioning was in January 1995.
Design Water Analysis: Wastewater Chemistries